Check that the pipe outside diameter is within the coupling range. Clean the surface and remove dirt, grease, burrs and loose particles.

ALIGN THE CLOSURES
Align both coupling halves and engage the closing points on both sides. Confirm that the gasket is not pinched or displaced.
COUPLING INSTALLATION GUIDE
Recommended procedure for correct assembly and sealing

MARK & CENTER
Mark the center of the joint or repair area. Position the sealing sleeve evenly without twisting or folding it.

TIGHTEN EVENLY
Tighten the bolts gradually in a cross pattern. Maintain even spacing and apply the manufacturer's recommended torque.

POSITION BOTH HALVES
Place the upper and lower coupling bodies around the pipe. Ensure the gasket and gripping rings remain correctly seated.

INSPECT & PRESSURE TEST
Inspect the coupling, gasket position and gripping rings. Pressurize gradually and verify that no leakage is present before service.